The framing passed inspection on a Wednesday; by the next week, the plumbers owned the house. Week 4 was plumbing rough-in across all three master suites, and it put a real number on the question people actually search — bathroom plumbing rough-in cost: $22,865 of labor and rough materials that ends up completely invisible behind tile and drywall. And by Friday, February 27, a City of Bothell inspector had already signed off on all of it: plumbing inspection passed, first visit. Here’s where that money actually went.

Open framed walls that set the bathroom plumbing rough-in cost on a three master suite remodel on NE 190th St in Bothell, WA
Open framing from the weeks before — the wall cavities the plumbers spent Week 4 filling with supply, waste, and vent lines.

The Week 4 schedule, day by day

Straight from our daily logs:

Day Logged work
Mon, Feb 23 No log entry — the pipe runs were already chalked out in Friday’s MEP mapping
Tue, Feb 24 No log entry posted
Wed, Feb 25 Plumbing rough-in in progress across the suites
Thu, Feb 26 Plumbing rough-in continues
Fri, Feb 27 Plumbing inspection passed — City of Bothell, first visit

Where does $22,800 of plumbing actually go?

Three places, roughly in this order. First, waste and vent lines — the big-diameter drain pipes that have to slope correctly through floors and walls, and the vents that carry sewer gas up through the roof. Second, supply lines — hot and cold runs to every vanity, toilet, and shower valve. Third, drains set in exactly the right spot, which matters more than anything else in a tiled shower: the drain location decides how the floor slopes before the first piece of tile is cut.

What it does not include: anything you’ll ever look at. Faucets, toilets, shower heads, and valve trim arrive months later from a separate 73-item fixture package (roughly $21,900 through Ferguson). Rough-in is the bones.

Why don’t three bathrooms in the same house cost the same to plumb?

Because they aren’t the same bathroom. Master 1 is a full rebuild with a curbless shower — the drain and the slope live inside the floor structure instead of on top of it, and a double vanity means two complete supply-and-waste sets. Master 2 is a brand-new bathroom built where closets and hallway used to be, so every single line is new — but the layout is simpler. Master 3 is an extension with the shortest runs and a single vanity. Same street, same week, three different bills:

Bathroom plumbing rough-in cost by suite

Master 1 — curbless shower, double vanity

$10,426

Master 2 — all-new bathroom

$7,136

Master 3 — extension

$5,303

Total

$22,865

If you’re researching bathroom plumbing rough-in cost for your own project: the honest per-bathroom range here was $5,300 to $10,400 for rough-in labor, and the single biggest cost driver wasn’t square footage — it was what the floor had to do (curbless drains and heated-floor prep at the top, a standard layout at the bottom).

What did the plumbing inspection check?

Before a single wall closed, the city verified the system under pressure: supply lines pressure-tested and checked for leaks, drain and vent sizing matched to fixture counts, slope on every waste run, approved materials, and protection plates where pipes pass through studs. It’s the same logic as the framing inspection the week before — check the work while it can still be seen.

Friday’s pass made it two for two: framing (Feb 18) and plumbing (Feb 27), both approved on the first visit. Two more checkpoints were still ahead — insulation (Mar 30) and the shower-membrane flood test in all three suites (May 5) — and spoiler from the end of the job: those passed first-visit too.

Framed walls and open ceiling cavities during plumbing rough-in week on NE 190th St in Bothell, WA
The before picture: by Friday these cavities held pressure-tested pipe, signed off by the City of Bothell.

Project numbers — Week 4

  • Total project: $328,828 (three master suites, incl. tax)
  • Bathroom plumbing rough-in cost, all three suites: $22,865 — 7.0% of project
  • The spread: $10,426 (M1, curbless shower) · $7,136 (M2, all-new bath) · $5,303 (M3, extension)
  • What it bought: every supply, waste, and vent line in three bathrooms — pressure-tested and city-approved before the walls closed

Where Week 4 sits in the 22-week build

Week 4 of 22 · Demolition → Framing (wks 1–3) · Rough-in (4–9) · Drywall (10–12) · Tile & counters (13–17) · Paint & finish (18–20) · Closeout (21–22)

Frequently asked questions

How much does bathroom plumbing rough-in cost?

On this Bothell project, bathroom plumbing rough-in cost ran $5,303 to $10,426 per bathroom — $22,865 across three master suites, about 7% of the total budget. The spread came down to layout: a curbless shower with in-floor drain work and a double vanity sat at the top of the range, a compact single-vanity extension at the bottom. Fixtures are a separate cost.

What does a plumbing rough-in inspection check?

The inspector verifies the system before walls close: supply lines under pressure test, drain and vent sizing matched to the fixture count, correct slope on waste runs, approved materials, and nail plates where pipes pass through framing. On NE 190th St the City of Bothell passed all three suites on the first visit, February 27.

Does plumbing rough-in include the fixtures?

No. Rough-in is only the in-wall and in-floor piping — supply, waste, vents, and shower valves. The visible fixtures (faucets, toilets, shower heads, trim) install at the end of the project during finish plumbing; on this remodel they came from a separate 73-item fixture package selected during design.

Next week the HVAC crew takes over — bath fans, ducts, and the $5,000 nobody ever sees. That’s Week 5. Follow the full project journal here.