This is Week 1 of our 22-week project journal from a three-master-suite remodel on NE 190th St in Bothell, WA — a completed project we’re documenting week by week, with real numbers.

On February 3, 2026, our crew carried in floor protection, dust barriers, and HEPA air scrubbers — not sledgehammers. That’s what the first morning of a bathroom demolition in an occupied home actually looks like. The family stayed in the house for the entire 22-week remodel, which means Week 1 was less about tearing things out and more about making sure the rest of the home never felt like a job site.

Temporary floor protection and dust barriers installed before bathroom demolition in occupied Bothell home
Day 1: protection goes in before a single wall comes down.

What gets protected before demolition starts?

Before any demolition began, we spent the first day on temporary protection: hardwood floor coverings on the entire first floor, both stairwells wrapped (walls, railings, and carpet), zip-wall dust barriers isolating the second-floor work zone, and portable HEPA air scrubbers running on the first floor for dust mitigation. On this project, that protection line item was carried at $0 to the client — it’s built into how we price demolition, because we don’t treat “keeping your house livable” as an upgrade.

Dust barrier zip walls isolating second floor bathroom demolition work zone
The second-floor work zone, sealed off from the rest of the house.

How do you demo three bathrooms at once?

All three master suites were demoed in one coordinated week: the corner tub, shower, linen closet, floors, vanities, and plumbing fixtures in the first suite; closet systems in the second suite, carefully removed intact and stored in the basement for the owners’ future re-use; and the tub, toilet, vanity, and flooring in the third. We also opened only the specific flooring and drywall needed to route new plumbing and electrical — controlled cuts, not blanket gutting, because every extra opening is drywall someone pays to patch later.

Master bathroom demolition in progress — corner tub and shower removed, Bothell WA remodel
Suite one, mid-demo: tub, shower, and vanities out.
Bathroom demolished to studs and subfloor during three-suite remodel
Down to studs and subfloor — controlled cuts only where new plumbing and electrical will run.
Controlled demolition opening for new plumbing routing in occupied home remodel
Openings are planned, not improvised: every extra cut is drywall someone pays to patch later.

What does demolition cost on a project like this?

Real numbers from this project: demolition across the three suites ran $16,038 of the $328,828 total project (incl. WA sales tax) — just under 5%. That bought a full week of a protected, dust-controlled teardown of three bathrooms, debris hauling into a dedicated dumpster, and a quality-control walk at the end of the week before framing started.

Project numbers — Week 1

  • Total project: $328,828 (three master suites, incl. tax)
  • Demolition (all three suites): $16,038 — 4.9% of project
  • Temporary protection: $0 line item — included in our demolition pricing
  • Why it matters: a protected demo prevents the most expensive change order of all — repairing the parts of your home you weren’t remodeling
Debris removal during master bathroom demolition Bothell remodel
Debris out daily — the contract requires a clean site every day, and we mean it.

The Week 1 schedule, day by day

Straight from our daily logs — this is the actual working schedule, not a reconstruction:

Day Logged work
Tue, Feb 3 Temporary protection installed; light demolition begins
Wed, Feb 4 Full interior demolition, all three suites
Thu, Feb 5 Interior demolition continues
Fri, Feb 6 Demolition complete; debris out; suites down to studs and subfloor
Mon, Feb 9 Final demo pickup + project-manager QC walk against the drawings

Demolition cost by suite

Suite 1 (main)

$6,534

Suite 2

$6,534

Suite 3

$2,970

Total

$16,038

Client price, from the signed contract. Suite 3 was a smaller footprint with no closet-system salvage work.

Where Week 1 sits in the 22-week build

Week 1 of 22 · Demolition → Framing (wks 1–3) · Rough-in (4–9) · Drywall (10–12) · Tile & counters (13–17) · Paint & finish (18–20) · Closeout (21–22)

Why does Week 1 set up the whole project?

By Friday, February 6, all three suites were down to studs and subfloor, debris was out, and our project manager walked every room against the drawings before a single new stud went up. The next Monday, framing material was delivered — Week 2 is where the new layouts start taking shape, including a brand-new walk-in closet framed from scratch.

End of week one bathroom demolition complete, ready for framing — NE 190th St Bothell
End of Week 1: clean, stripped, and verified against the drawings.
Quality control walk after demolition before framing begins
The QC walk — every room checked against the plans before framing starts.

Frequently asked questions

Can you live in your house during a bathroom remodel?

Yes — if the work zone is properly isolated. On this project the family lived at home for all 22 weeks. The keys are dust barriers sealing the work area, floor and stairwell protection on every path the crew uses, HEPA air scrubbers, and at least one fully functioning bathroom outside the work zone at all times.

How long does bathroom demolition take?

One master bathroom typically takes 1–2 days to demo. On NE 190th St we demolished three master bathrooms, including closet systems and selective flooring, in four working days — Feb 3–6 — with a protection day first and a QC walk after.

How much does bathroom demolition cost in the Seattle area?

On this Bothell project, demolition ran $2,970–$6,534 per suite depending on scope — $16,038 total for three master bathrooms, including temporary protection of the occupied home and debris disposal. Smaller single-bathroom demos typically run less, but protection and disposal are the costs homeowners most often underestimate.